November 06, 2026

THE GOOD, BAD & UNFINISHED

 

How many promises have we been given about fixing our state’s transportation woes?  How many press conferences have been held, initiatives launched and million dollar studies conducted… and for what benefit?

I engaged the services of AI to do this research and generate a complete scorecard which you can access here.

THE GOOD NEWS:

There is a new train station in Windsor Locks  and another one is being built for Enfield (only 26 years after first being recommended).  Naugatuck too will get a new station as the Waterbury line remains closed (until May of ’27) for major upgrades.  Enjoy those bustitutes.

Renovations are underway for the interior of the beautiful Union Station in New Haven (complete with a new bar!).  A massive roof-like train shed for the track area is still just an unfunded drawing, but a pretty one at that.

Proposed, but not funded, train shed.

$340 million is to be spent over nine years upgrading three miles of track between Bridgeport and Stratford.  Do the math:  that’s $113 million a mile.  Total budget for the New Haven line speed enhancements, $1.6 billion over nine years.

The Special Transportation Fund is projected to end FY2027 with a $209 million surplus… in the same year as two fare hikes.

Sixty new railcars from Alstom should start arriving for testing late this year.

Ridership on Metro-North is back to about 90% of pre-COVID levels, with weekends well above those numbers.  And on-time performance is running close to 98%, helped by padded schedules.

THE BAD NEWS:

Service (and ridership) on Shore Line East has still not been revived to pre-2020 numbers.  Unwilling to pay Amtrak to use its overhead wires and power, CDOT returns to diesel locomotives on what had been all-electric service.  Shoreline commuters can enjoy the nostalgia.  And the fumes.

Commuter rail fares in Connecticut went up 10% in just 10 months. The state didn’t fully fund the trains, so now you can.

Amtrak and Metro-North are still at war.

Seven highway workers have been killed in six years, fixing our highways.  Tragic and avoidable. Slow down!

Work continues on the $1 billion Walk rail bridge replacement in Norwalk. The promised completion of 2029 is now stretched out to 2031.

And “Shapiro’s Folly” continues to metastasize, as its housing developer-turned-visionary is now adding a tunnel to his proposed $50 billion bridge crossing Long Island Sound.  Why talk about building one thing we can’t afford, when you can build two?

THE UNFINISHED:

This list is the longest as our memories are too short to keep up with all we’ve been promised over the years.

How many of us remember the 20-year plan to rebuild the Hartford viaduct on I-84, since shelved and rolled into yet another study?  Or the 20+ year effort to build an interchange between the Merritt Parkway and Route 7 in Norwalk, soon to be restarted in late ‘27?

Whatever happened to the study to electrify the Hartford, Waterbury and Danbury rail lines which was due in 2025?

Or the long-promised West Hartford train station on the Hartford line, now 30% designed and 0% funded?

And yes, who can ever forget Governor Lamont’s 2019 pledge known as “30-30-30”, promising a 30 minute ride from Hartford to New Haven (now 45 minutes, at best), 30 minutes from New Haven to Stamford (now 65 minutes on average) and 30 minutes from Stamford to NYC (now 58 minutes in peak hours)?

Our state loves to solve problems by “studying” them… over and over.  Studies, though costly, are cheaper than real solutions.    Real fixes cost money which our lawmakers seem reluctant to find.

As one wag pointed out on social media “Goals are sold as accomplishments”, and so are more studies.

AI SCORECARD - The Good, the Bad the Unfinished

 

The Good, the Bad, the Unfinished

Produced using AI for “Talking Transportation” – November 2026.  All opinions are those of Claude AI.

Original query:  “Itemize long promised studies by the Connecticut Department of Transportation seen over the last 15 years … comparing what was promised as a goal and what was delivered in terms of change to the better… which ones failed and which one still have not finished their work.

Scorecard

 

Project

First promised

Promised outcome

Where It Stands Now

Verdict

Hartford Line

2004 study

New commuter service, New Haven–Springfield

Running since June 2018; 22 weekday round trips

Good

Waterbury Branch

2010 study

Better service, accessible stations

Signals and sidings by 2022; station rebuilds through 2028

Good, late

Let's Go CT

2015

$100B, 30-year rebuild

Never funded

Bad

Highway tolls

2009 onward

~$1B a year in revenue

Abandoned; truck fee budgeted at ~$62M

Bad

Danbury electrification

2006 study

Electric service to Danbury

Still diesel

Bad

Barnum Station in Bridgeport

2013–2014

Opening by 2018, then 2021

Still "planned"

Bad

I-84 Hartford viaduct

~2006

Replace the viaduct

Re-studied; federal funding dashboard says cancelled

Unfinished

Route 7/15 interchange

2005 construction

Full interchange

Construction may start 2027

Unfinished

Walk Bridge

2023 groundbreaking

Done by 2029

Now 2031; grant money runs to 2032

Unfinished

30-30-30 / TIME for CT

2019

10 min saved by 2022, 25 by 2035

Replaced by TIME-1, target 2035

Unfinished

Electrification study of branch lines

2023

Report by end of 2025

"Nearing completion"

Unfinished

Hartford Line additional stations

2004

Enfield, West Hartford, Newington, North Haven

Enfield opens 2030; others unfunded

Unfinished

The good: delivered, if late

Hartford Line. Service launched June 16, 2018, more than doubling trips in the corridor. It now runs 22 weekday round trips on top of Amtrak, and had fully recovered pre-pandemic ridership by 2024. The one genuine success. (CTDOT, Hartford Business)

Waterbury Branch. A 2010 CTDOT study identified fixes. Then nearly a decade passed before real money arrived. New signals and passing sidings let CTDOT add seven trips in summer 2022. All six stations are being rebuilt from 2025 to 2028 for about $193 million, with buses replacing trains July 2026 to May 2027. Good outcome, glacial pace. (NVCOG, Metro Magazine)

The bad: shelved or failed

Let's Go CT (2015). Governor Malloy proposed a 30-year, $100 billion program without saying how to pay for it. His own finance panel found more than $40 billion in options in January 2016. None stuck. (Bond Buyer, CT Mirror)

Highway tolls. The state spent over $20 million on CDM Smith and Cambridge Systematics studies since 2009, plus a $10 million study approved in 2018.  The 2018 report alone cost $2,035,000, about $23,391 a page. It proposed 82 gantries raising roughly $1 billion a year. Governor Lamont dropped tolls for a truck Highway Use Fee that DRS said would raise about $90 million a year. The official forecast: $60.8 million in FY2025, $61.7 million in FY2026. (CT Senate GOP, Yankee Institute, News 12, OFA)

Danbury Branch electrification. Phase I wrapped in 2006; Phase II began November 2007 and ended with a final report in 2016. In 2006, electrifying South Norwalk to Danbury was pegged at $37 million, $127 million with new equipment. Never built. Still diesel. (CTDOT, Phase II site, Phase I report)

Barnum Station, Bridgeport. Bridgeport Mayor Finch hoped it would be built by 2018.  By 2018 the target was 2021, at $300 million.  It remains a “planned station”. (News 12, CT Post, Wikipedia)

The unfinished: still studying, still building

I-84 Hartford viaduct. Planning began about two decades ago. In 2016 CTDOT settled on a lowered highway. In 2019 it pulled the I-84 study and swapped in a three-year regional mobility study. That report landed in late 2023; its big pieces still face state and federal environmental review. The federal permitting dashboard now lists the I-84 Hartford Project as cancelled. Meanwhile the old viaduct gets bridge rehab through July 2027. (CT Mirror, Hartford Business, AASHTO Journal, Permitting Dashboard, CTDOT)

Route 7/Merritt Parkway interchange, Norwalk. Construction began in 2005, was stopped by a lawsuit, and was cancelled in 2006. A new study followed, then a May 2023 environmental assessment. The $175 million project may start in 2027. Twenty-two years from first shovel to second. (Project history, EA, CT Construction Digest)

Walk Bridge, Norwalk. At the May 2023 groundbreaking, completion was expected in 2029. CTDOT's FAQ now says 2031. The federal grant's end date moved from 2030 to 2032, and obligations rose 37% to $947 million. (Mass Transit, Walk Bridge FAQ, HigherGov)

30-30-30 / TIME for CT. Lamont's 2019 pledge became an $8–$10 billion plan promising 10 minutes saved by 2022 and 25 by 2035. The 2022 milestone came and went. Its successor, TIME-1 ($1.6 billion, 90 mph), targets 2035 and starts with a 3-mile Bridgeport–Stratford stretch. (CTDOT TIME for CT)

Electrification study (Hartford, Danbury, Waterbury lines). Launched August 2023 with a promised finish by end of 2025. CRCOG's June 2026 report says it is "nearing completion." No report yet. (CTDOT, CRCOG)

Hartford Line additional stations. Enfield was in a 2004 recommended action. It broke ground Oct. 28, 2026, with completion in fall 2030. Twenty-six years.  West Hartford sits at 30% design with no construction money; Newington has concept drawings. (Wikipedia, Hartford Business, CRCOG)

The pattern

Studies finish on time far more often than projects do. When a study's answer is expensive, the fix is usually another study. The deadlines that slip are the ones riders and drivers actually feel.

Sources for details

•       CTDOT: Hartford Line Regional Vision

•       Hartford Business: Enfield station groundbreaking

•       CRCOG: Hartford Line overview, June 2026

•       Wikipedia: Enfield station

•       NVCOG: Waterbury Line Improvement Strategy

•       Metro Magazine: Waterbury Line station upgrades

•       Bond Buyer: Let's Go CT

•       CT Mirror: Transportation finance panel

•       CT Senate GOP: Tolls FAQ

•       Yankee Institute: Cost of 2018 tolls study

•       News 12: Highway Use Fee

•       OFA: Consensus Revenue Estimates, Nov. 2024

•       CTDOT: Danbury Branch Electrification Study

•       Danbury Branch Phase II site

•       Danbury Phase I Final Report

•       News 12: Bridgeport to design second station

•       CT Post: Barnum Station expectations

•       Wikipedia: Barnum station

•       CT Mirror: Hartford highway realignment

•       Hartford Business: Elevated option ruled out

•       AASHTO Journal: Greater Hartford Mobility Study

•       Federal Permitting Dashboard: I-84 Hartford Project

•       CTDOT: I-84 Sigourney Street bridge rehab

•       Route 7/15 Project History

•       Route 7/15 Environmental Assessment, May 2023

•       CT Construction Digest: Route 7/15 timing

•       Mass Transit: Walk Bridge construction begins

•       Walk Bridge FAQ

•       HigherGov: Walk Bridge federal grant

•       CTDOT: TIME for CT map

•       CTDOT: Electrification study press release

THE GOOD, BAD & UNFINISHED

  How many promises have we been given about fixing our state’s transportation woes?  How many press conferences have been held, initiatives...