Connecticut seems to be surviving the recent series of winter storms the way it always does: with salt, overtime, and lowered expectations. Life must go on and we’re all counting on CDOT to keep us moving.
So kudos to their 900 drivers
and 650 trucks that worked tirelessly to first, pre-treat some 10,000 “lane
miles” our state highways with salt brine, then plow the snow when it came.
If only our municipalities did
as good a job.
Drive from town to town and
you’ll see a vast difference in road clearing.
In some, because cars were taken off the road before the storm, streets
are clear. In others where cars were
left parked at the curb, it may take days to chisel them out from the icy berms
caused by plowing… like some sort of archeological dig.
Still to be excavated as well are
dozens and dozens of bus stops across the state.
Kudos also to our railroads
which, even in the teeth of a giant snow and ice storm, kept service running,
albeit at a reduced level. Where other
states’ railroads pre-emptively shut down before the storm (think NJTransit),
Connecticut’s trains kept running.
Amtrak did what Amtrak always
does in a storm: run enough trains to claim victory while canceling enough to
remind you who they are. A week later
and they’re still struggling.
As
I wrote last week, rail riders deserve open waiting rooms and cleared
platforms at stations (a service usually provided by local towns). But one experiment in keeping platforms clear
of ice and snow without using tons of rock salt has proven something of
a disappointment.
I refer to the state’s boldest
experiment yet: electrically-heated station
platforms in Darien! What could possibly
go wrong?
Back in 2023 a $32 million
contract was awarded by CDOT to rebuild crumbling station infrastructure at
Darien with new platforms heated by electricity… the first such project in the
state.
Now, explain the math to me: how will we pay some of the highest electric
rates in the US to melt snow vs the cost of human shovelers and bags of salt? Where’s the savings?
Admittedly there’s more to this
particular contract… better speakers for train announcements, improved
lighting, public information display boards, new elevators, ADA-compliant ramps
and sidewalks, and EV charging infrastructure. But we’re talking 32 million taxpayer
dollars!
Work on the whole project was
due for completion by the middle of this year, but almost immediately the
project ran into trouble.
Demolition of the old
platforms encountered unmapped underground utilities and unexpected
infrastructure requiring extra work. The
original steel railing vendor went bankrupt.
The completion date was pushed back and another $6 million was added to
the cost. Funny how that happens.
Last November the first half
of the project was finally done but they’re far from being finished. The elevators still aren’t running and only
half of the platforms have been replaced.
But how did the one new
electrically-heated platform do in the recent ice and snow storm? Just OK.
Heated Platform - Darien
The one platform that is
working (on the NY-bound side of the station) seems to have fared well in the
recent storm. But Eversource says it is
still waiting for paperwork from CDOT as well as state and local inspections
before they can throw the switch on the other side. And CDOT says they’re waiting for Eversource
to return a signed agreement.
And we’re all waiting for
Spring.
No comments:
Post a Comment