October 22, 2006

Tear Down the Stamford Garage???

Since its construction in the 1980s, the parking garage at the Stamford train station has been embroiled in controversy. Now comes word from the CDOT that it will probably have to be torn down and rebuilt, displacing the 800 or so cars that park there each day, possibly for years.

I don’t want to get into playing “the blame game” as to how we got into this mess, but rather, talk about some solutions, both long and short-term.

CDOT tells us that most parking garages only have a 40 year “life expectancy”, even with good maintenance. It seems that the old Stamford garage was not maintained and is falling victim to salt corrosion in its inner steel supports. This deterioration was known six years ago when CDOT took over control of the garage from the city of Stamford. Even when the new garage opened three years ago, CDOT considered closing the old garage for repairs, one floor at a time or structure-wide. But the pressures to add more parking over-weighed the call for maintenance and the new garage opened, adding to a total of 1900 spaces.

This Spring, CDOT consultants looked at two options… rehabilitation or demolition and replacement. A fix-in-place scenario was estimated to take nine years and cost $35 million. But a new garage could be built for $30 million, though no time estimate was given for this scenario. The engineers assure us the old garage is safe and will not suffer any “catastrophic failure”, though bits and pieces may start crumbling on cars.

Of course, CDOT has no money for either scenario. And even if demolition and a new-build is the option that’s chosen, $2 million in short term repairs will be needed to keep the old garage operable until it is torn down.

But this sad tale does have a silver lining: a new garage could be built bigger and taller than the old garage, adding badly needed additional spaces just as the planned Transit Way feeding cars to the station will open. Some mistakes made in the design of the newer garage, opened in 2003, could be learned from and not repeated.

Meantime, 800+ daily parkers at the Stamford station will be displaced… but to where? City of Stamford officials tell me they’re willing to help. The new garage near the Target store has 500 spaces and shuttles could be run from there. The Bell Street Garage, which has many spaces taken by local car dealers, could be opened up if those new cars were kicked out.

Clearly, towns like Darien, Norwalk and New Canaan will also be affected as displaced motorists seek parking at their train stations. Now’s the time for commuters in those towns to lock in a place on their town’s waiting list for permits at their stations.

CDOT is promising public hearings on this mess while fast-tracking design plans for a new garage, with plans due by the end of the year. But with massive construction underway in downtown Stamford for the new RBS headquarters right next to Swiss Bank, the prospect of a demolition and construction of a new station garage, doubtless lasting several years, will have a profound effect on area commuters and businesses.

I hope all of our elected officials get on with it… find the money, coordinate short-term parking solutions and expedite the needed work.

==============================================================
JIM CAMERON has been a Darien resident, transit activist and Metro-North commuter for 15 years. You can reach him at Cameron06820@gmail.com or www.trainweb.org/ct

No comments:

WASTING OTHER PEOPLES' MONEY

When we are spending our own hard-earned money, we are usually pretty cautious, especially in these tough times.  But when it comes to spend...